Decide Fast & Get 50% Flat Discount on This SPECIAL OFFER | Limited Time Offer - Ends In COUPON CODE: SAVE50%

Practice PMI PMI-SP Exam Questions

    1. Page: 1/66
      Total 326 Questions
    Question No 1
    Which of the following scheduling techniques identifies the successor activities and the predecessoractivities to assist the project manager in sequencing the project work?
    Choose the Choices:


    Question No 2
    You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?
    Choose the Choices:


    Question No 3
    Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
    Choose the Choices:


    Question No 4
    The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
    Choose the Choices:


    Question No 5
    Examine the figure given below: If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
    Choose the Choices:



    1. Page: 1/66
      Total 326 Questions